Client: Birse Rail |
Project: RuN Project - Nuneaton Resignalling
Value: £1.3m
Comprising of GRC and concrete troughing routes covering large areas between Rugby and Nuneaton. One-On have installed platform Off indicator bases, signal bases, platform SPT’s, LOC bases, lighting column bases and a variety of duct routes to encompass the above at Nuneaton station over it’s five platforms.
During the 2007, Rugby and Nuneaton Christmas blockade, One-On successfully completed 365m of 24 way platform duct routes including permanent reinstatement and also two large 7 lane UTX’s, these high profile works were completed in ten days and handed back to the client and TOC on time.